CORE – HANDS – OCTOBER 2020 AND DECEMBER 2020 – KERICHO COUNTY

Project Name: Road Improvement to access Kaplelach Primary school – Early Childhood Development and Education (ECDE) Centre. Project outcome was repair or road of 325 m – 87m for do-nou and 238m graveled , 660 m side drainage and 2 culverts installed – 6 rings each

A total of 31 community people and 2 technicians trained on road repair. The community people were mobilized to contribute 5t ballast and timber for culvert construction.